Items must be complete prior to Junior Week (6/12/22) -- 90 days before Junior Week!!
Work trim-out of girl's cabins (soffits / eaves /one window / prepare for paint / set up bunks)
Complete ceiling in boy's and girl's bath house and trim out
Clean cabinets and walls in girl's bath house
Install New Doors in Girl's Bath House
Complete Pavilion in Valley
Complete wiring in Tabernacle
Complete trim-out of boy's cabins
Run 100' water line to boy's bath house (reconnect sewer line)
Clean Pool (pick up dry trash and pressure wash)
Reinstall Pool Fence
Repair sidewalk from tabernacle to girl's side
Form and pour pad at electrical panel (girl's side)